Shipment 10 of GCGV Olefins Facility Project was successfully delivered

Publish time:2021-02-01 Number of clicks :3545 颜色: 尺寸:
GCGV, CKJV, PJOE united as one, in the global fight against the pandemic, with the will not be afraid of hardships and the tenacious spirit, makes a remarkable achievement. On January 24th, 2021, two olefins process modules separately weighing about 4,800 tons and 5,700 tons completed construction and loadout, and sailed away smoothly. So far, all 36 modules of the olefins separation and processing package of the GCGV Olefins Facility Project have been delivered, including 6 super-large process modules with a maximum weight of 7,000 tons.

The module construction peak period of shipment 10 overlaps with other large modules, and is only one month later than the delivery date of shipment 9. At the same time, the critical period of final assembly experienced extreme cold weather, which was an extremely severe test for on-site construction management, resource and human resource allocation.

The project team actively planned. Under the circumstance that the shop design, materials and site construction were affected by the pandemic, they allocated resources from various sides, optimized the site construction plan and process, and accelerated the construction progress through multi-disciplines cooperation. The client gave strong support, clarifying and coordinating to solve problems with high priority. On January 19th and 21st, 2021, the two modules with a total weight of more than ten thousand tons were successfully transported on board after close and orderly operation by the shipping team.