Jidong Oilfield Steel Jacket Offshore Platform Successfully Delivered

Publish time:2023-03-23 Number of clicks :2227 颜色: 尺寸:


On March 18, 2023, the steel jacket offshore platform of Nanpu 1-3 Area rolling development Project of Jidong Oilfield successfully completed all construction work in PJOE and was transported to the offshore installation site.


Since the construction of the project started on November 21, 2022, PJOE has cooperated with China Petroleum Pipeline Bureau(the client), Sinopec Shengli Offshore Inspection, Tangshan Zhongyou Construction Supervision Co., LTD., to quickly respond to the demand for early delivery of the project for offshore installation, and tried its best to speed up the construction and strive for early shipment.


On February 9, 2023, the first shipment of the project -- jacket, piles and trestle were delivered successfully.


On March 15, 2023, the construction and commissioning completion ceremony of the project was held.




Yang Hongsheng, assistant general manager of PetroChina Jidong Oilfield Company, congratulated on the successful delivery of the project and thanked all the personnel for their hard work. He pointed out that Dagang Oilfield Construction Company and PJOE cooperated closely with each other, spared no effort and lived up to expectations, showing their professional and excellent construction strength and dedicated and practical work style, which ensured the high-quality and early delivery of the project, laid a good foundation for the subsequent construction work, and also laid a good foundation for the good interaction and deepening cooperation between all parties in the future.


Cao Yunsheng, CEO of JUTAL, extended a warm welcome to the guests attending the completion ceremony. He said that jackets are traditional advantage projects of PJOE. The construction process is mature and stable, and the jacket weighing 23,000 tons has been successfully built and delivered. At the same time, in recent years, PJOE has steadily ramped up large-scale module construction, with the 10,000-ton core process module construction capability, which has created a good foundation for the rapid promotion of the execution of the project. In the process of project planning and construction, the client and partners showed the precious spirit of high responsibility, full support, sinking the front line and pragmatic responsibility, which set a good example for the project to work on time and deliver on time. We hope that all parties will strengthen communication and exchanges in the future and create opportunities for in-depth cooperation. PJOE will continue to provide high-quality, reliable, professional and efficient services.


On March 18th, 2023, the offshore platform loadout completed and sailed away.